Project history

Six jobs, and the number that mattered on each

Client names withheld by agreement. Drop counts, schedules and test results are exactly as recorded.

Project case studies

Round Rock · 2026

Colocation suite build-out

Scope. 18 cabinets in a leased colo suite, greenfield. Structured copper and fiber cross-connect, overhead tray, grounding, and full documentation.

The hard part. Their previous suite had been point-to-point patched and had become unworkable inside two years. The whole design brief was "make sure that can't happen again," which meant patch fields sized with real headroom rather than filled on day one.

18Cabinets
1,240Terminations
100%First-pass

Austin · 62,000 sq ft · 2026

Tech campus tenant fit-out

Scope. 640 Cat6A drops across three floors, two IDF closets, and a fiber backbone to the building MDF, on a nine-week GC schedule with hard milestone dates.

The hard part. The ceiling grid went in behind us on a rolling basis, so rough-in had to lead the drywall crew by exactly the right margin — too early and we blocked them, too late and we'd be cutting ceiling.

640Drops
4 daysEarly
0Retests

San Marcos · 2025

Distribution warehouse Wi-Fi

Scope. Handheld scanners dropping connection in the racking aisles, costing real picking time. Another vendor had quoted twelve additional access points.

The hard part. Telling them the truth. An on-site survey showed the APs were mounted at truss height, above the racking, so the aisles were in shadow. We moved fourteen and added six — roughly half the other quote.

20APs total
6Added, not 12
0Drops since

Austin · 2025

Outpatient surgical center

Scope. New IDF, 210 Cat6A drops, and redundant fiber paths between closets for a facility that cannot lose network during procedures.

The hard part. Every hour of work happened between 7pm and 5am, inside infection-control containment, with negative-pressure barriers and daily ICRA sign-off. Zero procedure days affected.

210Drops
2Diverse fiber paths
0Days impacted

Georgetown · 2025

Municipal IDF remediation, 6 closets

Scope. Fifteen years of undocumented cable across six closets in three city buildings. No labeling, no schedule, and a standing rule that nobody unplugged anything.

The hard part. Proving what was dead. We toned and verified every run before removing anything — 38% turned out to be abandoned, which code required us to remove anyway. Nothing live was interrupted.

6Closets
38%Cable abandoned
0Outages

San Antonio · 2024

Plant floor network expansion

Scope. Industrial Ethernet to 46 machine cells, hardened enclosures, and fiber ring topology so a single cut can't take down the line.

The hard part. Everything ran in conduit through an environment with welding, grinding dust and washdown. Standard commercial cable would have failed; the pathway design cost more than the cable did.

46Machine cells
RingFiber topology
2Shutdown weekends

The pattern

Half of these started as somebody else's job

Not because those contractors were incompetent — because the documentation stopped when they drove away, and two years of undocumented change is what actually breaks a cable plant. Handing you the paperwork isn't a courtesy. It's the part that determines whether the install holds up.

Get a scoped quote

Next step

Send us the drawings. We'll send back a real number.

Floor plans, a rack elevation, or a rough drop count is enough to start. You get a line-item quote — drops, pathway, terminations, testing, and documentation priced separately, so you can see exactly what you're paying for.

Get a scoped quote (512) 555-0188

Mon-Fri 6:30am-6:00pm - after-hours and weekend cutovers by schedule

Call (512) 555-0188